Animal Health Diagnostic Center
Project Description:
Construction authorization February 2008
Anticipated completion date: May 2010
Project size of 125,000 gsf
Project Budget: $80.5M
Architect: CUH2A Architecture, Engineering, Planning

Project Team:
John Keefe, Project Manager
Sue Hartman, Sr. Project Coordinator
Art Thompson, Construction Manager
![]()
Physical Science Building
Project Description:
Construction authorization September 2007
Anticipated completion date: October 2010
Project size of 197,000 gsf
Project Budget: $140,000,000
Architect: Burt Hill, Inc Architects/Engineers with Koetter Kim Associates, Architects

Project Team:
Gary Wilhelm, Executive Project Manager
Mike Husar, Sr. Project Manager
Ruth Howell, Assoc. Project Manager
Marcela Frink, Project Coordinator
Greg Crossett, Sr. Construction Manager
Marijane Johnson, Construction Manager
Kaz Hattori, Quality Control Manager
![]()
Milstein Hall
New building to house the architecture program elements.
Current Status: Awaiting construction
Client: College of Architecture, Art and Planning
Client Representative: John McKeown

Project Team:
Andrew Magre´, Executive Project Manager, Associate University Architect
Mike Swartwout, Project Manager
Tammy Johnson, Project Coordinator
![]()
Merrill Sailing Center
Project Description:
Design and build a new facility to replace the existing structures on east shore of Cayuga Lake.
Current Status of Project: Substantially complete
Anticipated completion date: April 2009
Client: Athletics
Client Representative: Alan Gantert

Project Team:
Mike Swartwout Project Manager
Tammy Johnson, Associate Project Manager
![]()
Herbert F. Johnson Museum of Art Expansion
Renovate existing building and construct an addition to better accommodate the museum’s collections and programs.
Current Status: Design
Client: Herbert F. Johnson Museum of Art
Client Representative: Peter Gould, Associate Director

Project Team:
Michael Swartwout, Project Manager
Tammy Johnson, Associate Project Manager
![]()
Weill Hall
Project Description:
Building will integrate life sciences with physical, engineering and computational sciences while providing a campus-wide access to state-of-the-art technologies. Please visit http://lifesciences.cornell.edu
Construction began August 2005
Completed September 2007
Currently completing closeout.
Projected size of 265,000 gsf
Project Budget $157,000,000
Architect: Richard Meier & Partners, NYC, NY

Project Team:
Jim Pung, AIA, NCARB, Senior Project Manager
Darlene Hackworth, Project Manager
Susan Drew, Senior Project Coordinator
Brian Brown, Construction Manager
Kaz Hattori, Quality Control Manager
![]()
Computing and Information Science Project
Building proposal for the Faculty of Computing and Information Science in the College of Engineering.
Current Status: Concept Phase
Client: Faculty of Computing and Information Science and the College of Engineering
Client Representative: Pat Musa (Computing and Information) and Cathy Long (Engineering)
Project Team:
Christine Carstensen, Project Manager
Ruth Howell, Associate Project Manager
Brian Brown, Construction Manager
![]()
Cornell Rowing Center
Current Status: Design Phase
Client: Cornell Athletics

Project Team:
Bob Stundtner, Project Manager
Tammy Johnson, Associate Project Manager
![]()
Riley-Robb Biofuels Research Laboratory
Construction began: February 2008
Construction Completion Date: April 2009
Architects: SWBR Architects with M/E Engineering

Project Team:
Rob McCabe, Project Manager
Chris Jung, Project Coordinator
![]()
Plantations Welcome Center
Current Status: Design Phase
Client: Cornell Plantations
Client Representative: Don Rakow, Director

Project Team:
Christine Carstensen, Project Manager
Ruth Howell, Associate Project Manager
![]()
Statler Hall and Auditorium Renovation
Current Status: Construction
Client: School of Hotel Administration
Client Representative: Bill Dowdell
Project Team:
Christine Carstensen, Project Manager
Ruth Howell, Associate Project Manager
![]()
Central Avenue Parking Garage
Current Status: Feasibility Study
Anticipated completion date: TBD
Client: Transportation & Mail Services
Client Representative: Andrew Eastlick

Project Team:
Andrew Magre´, Executive Project Manager, Associate University Architect
Michael Swartwout, Project Manager
Tammy Johnson, Associate Project Manager
![]()
Humanities Building
Proposed addition to Goldwin Smith Hall.
Current Status: Feasibility Study Phase
Client: College of Arts and Sciences
Client Representative: Jane Pedersen

Project Team:
Gary Wilhelm, Project Director
Ruth Howell, Associate Project Manager
![]()
Olin Library Life Safety
Provide Life Safety, HVAC and program renovations within the upper levels of Olin Library.
Current Status: Design Phase
Client: University Library
Client Representative: John Hoffmann

Project Team:
Darlene Hackworth, Project Manager
Catherine O'Hora, Sr. Project Coordinator
![]()